European Communcations Office

ECC Work Programme Database

   
Work Item details
Reference PT1_37
Short Name ECMandate_40GHz
ETSI Workitem
ETSI Deliverable
Subject EC Mandate on 40 GHz mm Wave 5G (MFCN)

Related WI PT1_39
PT1_46
FM44_44
Scope Response to the EC Mandate to develop least restrictive harmonised technical conditions suitable for next-generation (5G) terrestrial wireless systems for 40.5-43.5 GHz


Deliverable CEPT Report
Responsible group ECC PT1 - ECC PT1
Start date 03-07-2020
Target date 04-11-2022
Public Consultation 01-07-2022
Permanent Work Item False
Comments

Refer to EC “Mandate to CEPT to develop least restrictive harmonised technical conditions suitable for next-generation (5G) terrestrial wireless systems for priority frequency bands above 24 GHz” regarding Tasks 1, 2 and 4

Deliverables:

  • March 2021 : draft for public consultation
  • July 2021: final report
ECC #55 tasked ECC PT1 to study coexistence at the 40.5 GHz boundary between MFCN in 40.5-43.5 GHz and uncoordinated satellite earth stations in 39.5-40.5 GHz: ECC(21)027 Annex 07


Keywords 5G, 40GHz, EC
Worked by ECC PT1
Contact Peter Faris ([email protected])
Status Finalised
Triggered By EC Mandate


Progress Report

WI closed by ECC#60 following publication of CEPT Report 82