Scope This ECC Report will analyse the regulatory impact of moving to new solutions for NP in an all-IP environment. The report will describe the number portability scenarios in an all-IP environment, including different routing solutions and NP database interaction with the IP routing database. Following this analysis the regulatory impact will be assessed regarding the migration process, legacy issues and whether or not new regulations are required.
Deliverable ECC Report
Responsible group WG NaN - NaN2
Start date 31-05-2018
Target date 30-11-2021
Public Consultation 28-05-2021
Regular Work Item False
Comments
Keywords Number portability, IP, switching, IMS,
Worked by PT NPS
Contact Freddie McBride (Closed) (freddie.mcbride@eco.cept.org)
Status In Progress
Triggered By Portugal, Norway, Belgium and Hungary
Progress Report Work item approved at the 16th meeting of WG NaN (Reykjavik 29-31 May 2018).

NaN2 had two web meetings (08 December 2020 and 12 January 2021) to progress the work on the draft ECC Report NP in all-IP environment

During the 29th meeting the draft ECC Report was reviewed section-by-section. It was agreed that further web meetings would take place on 26 March 2021 and 23 April 2021 to progress the work.

Work on the draft report continued at a web-meeting held on 26 march 2021.